JOTP-011
5 December 2014
APPENDIX C. ENVIRONMENTAL TEST DESCRIPTIONS
ANNEX 1. CLIMATIC TESTS
b. Conditioning Temperature: Munitions are to be preconditioned to a
temperature of
10 °C above the water temperature.
c.
Test Levels: Rainfall rate = 100 mm/hour. Wind velocity = 18 m/s.
d.
Test Duration: 2 hours.
C.1-11 ICING.
Perform per MIL-STD-810, Method 521 on the munition in the unpackaged configuration when
applicable with medium loading (13 mm) ice thickness representing general conditions. Sea based
munitions may require an ice thickness of 75 mm in cases where extremely heavy loading is possible
for items on a ship deck.
C.1-12 CARGO AIRCRAFT DECOMPRESSION.
Perform Rapid Decompression testing in accordance with MIL-STD-810, Method 500,
Procedure III using the following test parameters:
a.
Munition Configuration: Packaged munitions.
b. Conditioning Temperature: Munitions are to be preconditioned to laboratory
ambient temperature.
c.
Pressures: Initial pressure = 60 kPa. Final pressure = 18.8 kPa.
d.
Decompression Time: No longer than 15 seconds.
C.1-13 MOULD GROWTH.
Perform per MIL-STD-810, Method 508 on the munition in the unpackaged configuration when
applicable for a minimum of 28 days. This test should be conducted as a non-sequential test.
C.1-14 CONTAMINATION BY FLUIDS.
Perform per MIL-STD-810, Method 504 on the munition in the unpackaged configuration when
applicable. Test requirements are to be tailored according to the materials on the test article. This
test should be conducted as a non-sequential test.
C.1-5
For Parts Inquires call Parts Hangar, Inc (727) 493-0744
© Copyright 2015 Integrated Publishing, Inc.
A Service Disabled Veteran Owned Small Business