JOTP-011
5 December 2014
APPENDIX B. TEST PROGRAM FOR SURFACE AND UNDERWATER
LAUNCHED MUNITIONS
ANNEX 2. EMPIRICAL S3 TEST PROGRAM
TABLE B2-1. ENVIRONMENTAL TEST ASSET QUANTITIES FOR EMPIRICAL S3
PROGRAM
Inert
Live
Other Units or
Tests
Munitions1
Components
Munitions2
Sequential Environmental Tests:
---
---
Component Test Sequence (Static Fire/Burst)
10
---
---
Reduced BTCA Test Sequence
4
203
---
---
Dynamic Firing Test Sequence
24
---
---
Rough Handling Test Sequence
---
10
---
Rocket Motor Case Burst Test Sequence
Non-Sequential Environmental Tests:
---
---
3
12m Logistic Drop
1 each EID/ESAD5
---
1
Shipboard UNDEX Safety Shock
32 each EID/ESAD
1
---
HERO
20 each EID/ESAD
1
---
ESD
16
1
---
Lightning Hazard
---
1
---
Pressurization (Underwater Launched)
Totals
41
14
53
NOTE 1: Live munitions contain all safety critical components. They may contain mass simulants to replace
components that are unrelated to the munition safety (e.g., guidance, control). Configurations may vary according to
particular test objectives.
NOTE 2: Inert Munitions contain no energetic materials and may contain mass simulants to replace components that
are unrelated to the test objectives.
NOTE 3: Fully functional munitions suitable for firing safety tests.
NOTE 4: If the munition survives the rough handling drop test determine whether to dispose of the munition or to
disassemble for BTCA.
NOTE 5: Back-up EIDs may be required for the HERO test otherwise a damaged unit resulting from the
modification/instrumentation/testing processes may delay the assessment program.
NOTE 6: The requirement for 1 live munition for the direct strike lightning test may be tailored based on Nation
specific requirements.
B.2-3