JOTP-011
5 December 2014
APPENDIX B. TEST PROGRAM FOR SURFACE AND UNDERWATER
LAUNCHED MUNITIONS
ANNEX 2. EMPIRICAL S3 TEST PROGRAM
Systems or subsystems incorporating ESAD's must be tested while in the functional mode. At a
minimum, E3 assessment tests will include the following:
(1) One (1) live munition and 1 inert munition with 20 live sets of EID/ESAD's for
Lightning Hazard.
(2) One (1) inert munition with one instrumented EID/ESAD for HERO tests.
(3) One (1) inert munition with 32 live sets of EID/ESAD's for ESD tests.
d.
One (1) inert underwater munition for pressurization testing.
e. Additional inert munitions may be required for Operational and Maintenance Review as
described in Appendix H, Annex 3.
f. Additional live munitions will be required for Hazard Classification Testing per
TB 700-2.
g. Additional munitions will be required for Insensitive Munitions Tests per MIL-STD-
2105, STANAG 4439 and AOP-39.
h.
Four modified munitions will be required for Warhead Arena Trials.
i. Systems or subsystems incorporating firing circuits controlled by electronics must be
tested while in the functional mode if the threat is present when they are powered.
j.
Additional test assets may be required for fuze S3 testing per MIL-STD-331.
k. Additional test assets may be required for other safety tests determined to be necessary
to address special circumstances not considered in this document or as the result of marginal or
inconclusive test results throughout the overall S3 test program.
B.2-2
For Parts Inquires call Parts Hangar, Inc (727) 493-0744
© Copyright 2015 Integrated Publishing, Inc.
A Service Disabled Veteran Owned Small Business